Can a company invoke force majeure circumstances if the CCI certificate is submitted later than stipulated in the contract?

21.11.2025 07:35

Answers

Photo of lorina200215Lorina Fedan

Yes, it can. Late submission of a CCI certificate does not deprive a party of the right to invoke force majeure, unless the contract expressly provides that missing the deadline for submitting the certificate deprives of such a right. The courts distinguish between: * notification of force majeure must be timely, * the CCI certificate can be obtained and submitted later. Therefore, the delay in submitting the certificate is not, in itself, a ground for refusing to apply force majeure.